All four models from the BMW Group plant in Leipzig (from left): BMW 2 Series Gran Coupé, BMW 1 Series, BMW 2 Series Active Tourer, MINI Countryman (11/2024)
Digital construction planning is an essential part of virtual production planning. Construction-, system-. and logistics-planning are brought together digitally, thus reducing construction time and helping to collaborate on critical interfaces at an early stage. (10/2024)
In the so-called “centre brace”, construction began on the side buildings, i.e. company catering, energy and service center and the company fire department, as planned in summer. (10/2024)
Parallel to the position of the last pillar, the roof at the other end of the 300 by 500 meter long assembly hall is already being closed, windows are being installed and the first technical building equipment is being installed. (10/2024)
Production of the new BMW 2 Series Gran Coupé at BMW Group Plant Leipzig (11/2024)
Related Articles.
All four models from the BMW Group plant in Leipzig (from left): BMW 2 Series Gran Coupé, BMW 1 Series, BMW 2 Series Active Tourer, MINI Countryman ...
All four models from the BMW Group plant in Leipzig (from left): BMW 2 Series Gran Coupé, BMW 1 Series, BMW 2 Series Active Tourer, MINI Countryman (11/2024)
BMW Group Plant Regensburg: Production of the fully electric BMW iX1 (10/2024)
Related Articles.
Digital construction planning is an essential part of virtual production planning. Construction-, system-. and logistics-planning are brought together ...
Digital construction planning is an essential part of virtual production planning. Construction-, system-. and logistics-planning are brought together digitally, thus reducing construction time and helping to collaborate on critical interfaces at an early stage. (10/2024)
Related Articles.
In the so-called “centre brace”, construction began on the side buildings, i.e. company catering, energy and service center and the company fire ...
In the so-called “centre brace”, construction began on the side buildings, i.e. company catering, energy and service center and the company fire department, as planned in summer. (10/2024)
Related Articles.
Parallel to the position of the last pillar, the roof at the other end of the 300 by 500 meter long assembly hall is already being closed, windows are ...
Parallel to the position of the last pillar, the roof at the other end of the 300 by 500 meter long assembly hall is already being closed, windows are being installed and the first technical building equipment is being installed. (10/2024)
Related Articles.
The concrete pillar, which weighs around nine tons, is transported by a crawler crane to the intended location on the construction site. (10/2024)